| Notice ID: | 60102 |
| Notice Type: | Planned Service Outage |
| Critical: | Y |
| Notice Status Description: | Initiate |
| Reqrd Rsp Desc: | No Response Required |
| Posting Date/Time: | Dec 16 2025 8:04 AM |
| Subject: | JANUARY 2026 --- FGT ZONE 2 MAINTENANCE |
| Notice Effective Date/Time: | Jan 1 2026 9:00 AM |
| Notice End Date/Time: | Jan 31 2026 9:00 AM |
| Notice Text: |
FGT will be performing pipeline maintenance near FGT Compressor Station 8. This maintenance is scheduled to begin on January 5, 2026, and is to be completed by end of gas day January 31, 2026. During this maintenance FGT will schedule up to 1,025,000 MMBtu/day through Station 8. During normal operations FGT schedules up to 1,075,000 MMBtu/day through Station 8. |